Jackson Hospital West
Location
Market
Buildings
Market Sub Sector
Services
Sheet Piling
Client
Baker Concrete
Owner
Yates Contruction
Description
Ten temporary coffer cells
Division
ASAP Installations
Challenge
Installation required strict precision since sheet piles would serve as form board for the pile cap pour
Solution
Installation was performed with a precision tolerance of 2”-5” of distance between the sheet piles and the pile caps. This approach allowed the removal of the form board scope which saved time in the critical path of the foundations and deducted the cost of this activity. Sheet Pile material was re-used, which provided cost savings to the general contractor on the material supply. In addition, the recycling was completed in a manner that permitted a continuous operation in sync with the pouring of the caps and without requiring additional mobilizations.